Why CDBG Action Plans Get Amended (and What You Can Do)

CDBG amendments cost months. Learn the 10 common triggers and how to build a project inventory so funds get back to work faster.

Gavin Baum-Blake

Katherine Zobre

In January 2026, a nonprofit in Hot Springs, Arkansas, withdrew from a Community Development Block Grant (CDBG) award, leaving $45,000 in funds on the table. CDBG funds follow a strict process for reallocating funds. That’s not a huge sum, and the city handled it by the book. Staff first checked whether city departments could use the money for another project already budgeted, utility extensions in the same neighborhood. They concluded the funds would be better used on a different project that had a high likelihood of completion by the deadline. They then invited letters of interest from past grant recipients, scored the proposals, and heard presentations from two finalists. A 30-day public comment period runs until mid-December, with a final board vote on December 15.

Nearly a year after the partner withdrew, that $45,000 still hasn’t been put to work improving the community.

Amending an annual action plan isn’t a failure. Often it’s the responsible thing to do. But every amendment costs months of calendar time, staff hours, and margin on HUD’s timeliness test. There are several reasons Annual Action Plans get amended. Some of them can be seen coming before the money is awarded.

What triggers an amendment

Under 24 CFR 91.505, a grantee has to amend its plan when it makes certain changes. Under 24 CFR 91.505(a), a city must amend its plan to:

  • change its allocation priorities or how it distributes funds

  • carry out an activity that isn’t in the plan, including one using program income, recaptured funds or HUD reallocations

  • “change the purpose, scope, location, or beneficiaries of an activity”

Depending on the size of the change, the amendment will be either substantial or minor. Examples of substantial amendments include canceling an activity, creating and funding a new program, or changing an activity’s purpose, scope, or beneficiaries. Each community’s Citizen Participation Plan sets the threshold for a substantial amendment, usually based on a dollar amount or a percentage of the budget. Substantial amendments require public notice, a comment period of at least 30 days, a hearing, local approval, and submission to HUD.

In order to encourage jurisdictions to keep a steady pace of implementing programs and projects to improve their communities, HUD sets a timeliness test. Under 24 CFR 570.902, 60 days before the end of the program year, a grantee may hold no more than 1.5 times its annual grant in unspent funds. For example, if Springfield is awarded $1,000,000 annually, starting in 2025, by the end of October 2026, they need to have spent $500,000 of those funds (leaving a max of $1,500,000 in unspent funds). As that deadline approaches, the options become more limited.

Common reasons cities make substantial amendments

Setbacks

1. A program partner withdraws
The Hot Springs, AR award was for a neighborhood renewal project. It proposed building at least three affordable homes for sale to low- and moderate-income families. According to the city’s amendment, the partner withdrew after several meetings with staff about eligible activities and national objective requirements.

The lesson: Find and vet community development-based organizations well in advance through smaller projects or prequalification lists. The City and County of San Francisco’s Emerging Technologies Request for Qualifications list is a different context, but provides a model for building a deep bench of talent to draw from. 

2. The project turns out to be infeasible
Travis County, TX made a substantial amendment to the 2024 Action Plan, the County removed $150,000 for the design of the Northridge Acres wastewater project, which it “determined to be infeasible due to the need for significant financial participation and coordination among multiple stakeholders.” The amendment does not move the money to a new project. It lists the funds as available for reallocation to “one or more eligible CDBG activities.”

The lesson: If a project needs other partners’ money or cooperation, get those commitments in writing before it goes into the Action Plan. For complex, multi-partner projects, consider funding a smaller feasibility or planning step first. And when a project falls through, have a next use ready, so the funds don’t sit waiting for another amendment cycle.

3. The environmental review finds a problem
The City of Santa Clarita, CA budgeted funds for Newhall Community Center improvements. Its draft 2026–27 plan says the project was found ineligible “upon initiation of the NEPA environmental process,” “due to FEMA floodway regulations.” The city spent $4,021 on the review and is moving the remaining $1,444,431 to Creekview Park. It notes it is “reviewing this site’s eligibility.” Site evaluation and eligibility costs are eligible uses of funds under CDBG as long as the expenses are necessary, reasonable, allocable, and tied to an eligible activity or cost category. When a site is found ineligible, an amendment may be required, delaying implementation of the funds.

The lesson: You can’t always know in advance when a site will be evaluated as ineligible. However, having an inventory of potential, community priority sites as alternatives can substantially improve the turnaround time in using the funds on an eligible site.

4. The property turns out to need demolition, not rehab
Wilmington, DE moved $300,000 to demolish a property that had previously been on the list for rehabilitation. Ultimately the property was deemed beyond repair, requiring demolition. The property had boarded up windows for over 10 years before the rehabilitation and eventual demolition orders. Moisture related damage can push a property beyond the repair threshold within one year. While 10 years of boarded up does not in itself condem a property to demolition, longterm boarding without other stabilistation and maintenance efforts can allow moisture and structural damage to accumulate. 

The lesson:  Maintaining a vacant property registry or list, and specifically tracking abandoned properties can provide eligible alternatives in the event that a rehab project turns into a demolition project. 

Outside the city’s control 

5. An outside error or rule change forces a revision
Not every amendment starts at city hall. Pinellas County, Florida, is working through the third amendment to its CDBG Disaster Recovery (CDBG-DR) action plan. According to the amendment’s change log, it revises program budgets to address a HUD allocation error involving $126 million intended for the City of St. Petersburg’s Sunrise St. Pete program. It also increases the projected low- and moderate-income benefit percentages for the Homeowner Reimbursement and Homebuyer Assistance programs, removes the Strategic Relocation and Revitalization Program, and reserves $47 million for a joint County/City infrastructure project. It follows a substantial amendment in September that updated housing program eligibility, award methods, and administrative requirements.

The lesson: You can’t prevent someone else’s mistake, but you can control how fast you recover from it. When budgets, eligibility documentation, and maps are already organized, a correction becomes an update, not a rebuild.

6. The site stops qualifying as a low- and moderate-income area
In 2025, about 16 months into the work, Morgantown, WV completed, and HUD approved a “Timeliness Workout Plan” - a plan that helps jurisdictions keep projects on track by mandating incremental drawdown requirements. The Plan reviewed the Annual Plans from FY2019, FY2020, FY2023, and FY2024 and found several projects and sites requiring substantial amendments. Two CDBG activities were slow to start or ineligible. The change in eligibility was due to the Census Bureau “revised census tract and block group boundaries, making this site no longer in a Low/Moderate income block.” 

Good news that still requires an amendment

7. New needs, priorities or funding sources
Not every amendment is a problem. Travis County’s Consolidated Plan amendment does two things:

  • It adds Emergency Solutions Grant (ESG) funding. The amendment says Program Year 2027 “represents the first year that Travis County is eligible to receive ESG funding directly from HUD.”

  • It raises several priorities, including affordable rental housing, to reflect its PY2026 Community Needs Survey.

The lesson: Updating the plan when new data or new funding arrives is the system working as intended. The County amended its plan ahead of its first ESG year, not after the money arrived. Time your needs surveys and data updates to the planning calendar, so new priorities can go into the next Action Plan instead of a mid-year amendment. Current property-condition data can complement resident surveys by showing where needs are concentrated on the ground.

8. The scope of an approved project changes
Travis County, TX Creedmoor right of way project was ahead of schedule. The amendment, moving $500,000 from the design/engineering phase to construction phase is a sign of a successful project. The shift in funding “does not increase the total amount of funding allocated to the project.” But because the County’s Citizen Participation Plan treats a scope increase or decrease of more than 25% as requiring a substantial amendment, the project’s good news required the substantial amendment. 

The lesson: Know your own thresholds. Before moving money between phases of a project, check whether the move crosses your Citizen Participation Plan’s trigger. If projects routinely move from design to construction across program years, describe the activity in the Action Plan as covering the full project, not just one phase. If your thresholds regularly force amendments for routine changes, consider updating your Citizen Participation Plan, which requires its own public process.

9. Funds are left over in an earlier activity
Money left in an activity, whether it came in under budget, ran slower than planned, or ended early, doesn’t move to a new use on its own. Indianapolis’s proposed 2026 amendment, for example, reprograms more than $1.1 million in rollover funds from its 2024 Owner-Occupied Repair program to a rental housing project and the city’s Section 108 loan payment. The amendment doesn’t say why the funds were left over, and it doesn’t need to. What matters is that once the balance crosses the threshold set in the city’s Citizen Participation Plan, moving it requires a public process. Other jurisdictions with leftover funds include

  • Glendale, CA: amended to “repurpose unexpended funding from completed or cancelled activities.”

  • San Mateo County, CA: reusing funds “from activities that were canceled or did not draw down the full amounts awarded.”

  • Baltimore, MD: reallocated “liquidated and unspent” funds from program years 2020–2024.

The lesson: Review activity balances throughout the year, not just at year-end. Flag slow-moving activities early, and keep a short list of eligible, documented projects that could absorb leftover funds. A city that already knows where a balance should go can move it in one amendment cycle, well before the Timeliness Test, without scrambling for a replacement.

Every amendment is a race against the timeliness test

10. A timeliness deadline narrows the choice
HUD’s timeliness test allows a city to hold no more than 1.5 times its annual CDBG grant unspent, measured 60 days before the end of its program year. As that date gets closer, how fast a project can spend its funds can become the deciding factor. In Hot Springs, AK, the advisory committee weighed project readiness, expected completion schedules, and “the City’s need to expend CDBG funds in a timely manner.” It concluded that “funding improvements anticipated to be completed before June 2027 would best support the program’s current timeliness needs.” The selected project, rehabilitating a supportive residential care home, will make progress. The city notes that “additional funding and work would be necessary before the entire home could be occupied.” A September 2024 HUD policy memo update to the timeliness test to include a detailed escalation process: a warning letter, then a timeliness workshop and workout plan, then an informal consultation and possible loss of funds after repeated failures. 

The lesson: Track your timeliness ratio all year, so you know how much room you have before you have to choose a replacement project. Make readiness part of the original selection criteria, not just a tiebreaker when a deadline is close. Projects with eligibility, service area, and site conditions documented in advance can be both fast and high-impact, so the city doesn’t have to trade one for the other.

The pattern: the amendment isn’t the problem, the wait is

Group

Triggers

What speeds up the amendment

Setbacks

A partner withdraws (Hot Springs); a project proves infeasible (Travis County); the environmental review finds a problem (Santa Clarita); a rehab property needs demolition (Wilmington)

Vetted partners with commitments in writing, sites screened before the award, and alternate sites and properties already identified

Outside the city’s control

A HUD allocation error (Pinellas County); Census changes block groups resulting in  LMI changes (Morgantown)

A current project inventory with alternates already scoped, plus maps and plain-language summaries ready for public comment. When an outside change hits, the city can swap in a documented project and explain the change to residents quickly.

Good news

New funding and priorities (Travis County); a project’s scope changes (Travis County); funds left over in an earlier activity (Indianapolis)

Knowing your Citizen Participation Plan thresholds, reviewing balances throughout the year, and keeping ready projects to absorb funds

Amendments aren’t a sign that something went wrong. They’re how a plan stays honest when the facts change. Redirecting money through a public process is better than letting it sit in a project that can’t move. The 30-day comment period, the hearing and the council vote are there so residents can weigh in on where their community’s money goes.

The cost is time. Every amendment adds weeks of process, and when the city doesn’t already know where the money should go next, it adds months. In Hot Springs, nearly a year passed between the partner’s withdrawal and the board’s final vote, with $45,000 waiting the whole time. So the question isn’t whether to amend. It’s how quickly you can get from “something changed” to “the money is back at work.”

Build a ready-to-fund project inventory

The fastest amendments are the ones where the next project is already known. A project inventory is a standing list of eligible projects, sites and properties that are already scoped, with eligibility documented and the data kept current. When a trigger hits, staff choose from the list instead of starting a new search.

Check eligibility before a project goes on the list. For area-benefit activities, map the proposed service area against HUD’s Low- and Moderate-Income Summary Data (LMISD). Follow the rules in CPD Notice 24-04: you can’t average percentages across block groups, and you can’t prorate a partial block group. A service area that looks fine on a hunch can come in at 50.69% instead of 51%.

Tip: Use City Detect’s custom parcel groups to easily identify vacant and abandoned properties; Use City Detect’s custom areas to overlay eligible areas using LMI and eligible service area data. 

Document conditions, not just intentions. Several CDBG paths depend on evidence of physical conditions.

  • To qualify an area as slum or blighted under 24 CFR 570.208(b)(1), the area must meet a state or local definition. One way to qualify is showing that at least 25% of its properties have conditions such as “physical deterioration of buildings or improvements” or “abandonment of properties.” 

  • CDBG-funded code enforcement under 570.202(c) is limited to “deteriorating or deteriorated areas.”

  • Property-level condition data is the kind of evidence these rules call for.

Tip: City Detect property detections puts this baseline in your hands before you need it using Level 4 Issue filters to find the parcels with the highest level of physical deterioration. 

Screen sites early. A flood map check or a quick look at site history won’t replace a full environmental review. It can, however, catch the kind of problem that stopped Santa Clarita’s project before money is committed.

Identify properties before programs open. Repair, demolition and acquisition programs shouldn’t launch and then go looking for properties. Identify likely candidates in qualifying block groups ahead of time, along with alternates in case a rehab property turns out to need demolition.

Line up partners and commitments. Know which organizations can carry out the work. For projects that depend on other partners’ money or cooperation, get those commitments in writing before the project goes on the list.

Keep it current. An inventory is only as good as its data. Conditions change, block group boundaries and HUD’s income data get updated, and a site that qualified two years ago may not qualify today. Refresh the inventory at least once a year, ahead of the Action Plan.

Where City Detect fits

City Detect’s platform gives grantees a documented, parcel-level picture of conditions across their jurisdiction, so the inventory is built on current evidence. Teams can use it to:

  • check service areas against LMISD block groups

  • support slum/blight and code enforcement findings

  • identify and rank candidate properties for repair, demolition and acquisition programs

  • produce clear maps for hearings and Consolidated Plan meetings

To be clear about the limits: data won’t stop a partner from walking away, change council priorities, or fix an allocation error at HUD. What it can do is make sure that when something changes, the next project is already identified and documented.

City Detect detection data can support a variety of grants for needs assessment, condition assessment, compliance tracking, and reporting. Some of the grant categories include

  • CDBG/HOME

  • Historic Preservation

  • State Housing Authority Grants (See how Prescott Valley used City Detect in grant reporting)

  • Department of Transportation Safe Streets 4 All  (pavement and roadside conditions)

  • EPA Brownfield Assessment Grants

  • FEMA BRIC Grants (automated virtual inspection)

  • FEMA Hazard Mitigation Grants

  • FEMA Public Assistance Grants

Is this project ready for your inventory?

  1. Is the activity eligible, and is its national objective documented in writing?

  2. Does the service area match current LMISD geographies, calculated without averaging or prorating?

  3. Do you have recent evidence of conditions, not just a description of them?

  4. Has the site been screened for obvious environmental issues?

  5. Are partner commitments and cost-sharing confirmed in writing?

  6. For property-based programs, is there a list of eligible properties, plus alternates?

Amendments will happen. The communities that recover fastest are the ones that already know where the money goes next.

Want to see what this looks like for your jurisdiction? Download our CDBG Amendment Triggers resource below!

CDBG Amendment Triggers

CDBG Amendment Triggers

CDBG Amendment Triggers

3D wireframe grid perspective view. White lines create a box-like structure, receding into the distance.

Ready to Change Your Community?

3D wireframe grid perspective view. White lines create a box-like structure, receding into the distance.

Ready to Change Your Community?

3D wireframe grid perspective view. White lines create a box-like structure, receding into the distance.

Ready to Change Your Community?